A and B can separately complete a piece of work in 20 days and 30 days respectively. They worked together for some time, then B left the work. If A completed the rest of the work in 10 days, then B worked for : 

(a) 6 days 

(b) 8 days 

(c) 12 days 

(d) 16 days

1 Answer

+1 vote
by (71.7k points)
selected by
 
Best answer

Correct option (a) 6 days

Explanation: 

A’s 10 days work = 10×3 units/days =30 units

So, (60-30)=30 units of work would have been 

done by A and B both and it took time:

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.