Use app×
Join Bloom Tuition
One on One Online Tuition
JEE MAIN 2025 Foundation Course
NEET 2025 Foundation Course
CLASS 12 FOUNDATION COURSE
CLASS 10 FOUNDATION COURSE
CLASS 9 FOUNDATION COURSE
CLASS 8 FOUNDATION COURSE
0 votes
1.3k views
in Aptitude by (79.8k points)

20 men can do a piece of work in 18 days. They worked together for 3 days, then 5 men joined then. In how many more days is the work completed? 

(a) 12 days 

(b) 14 days 

(c) 13 days 

(d) 15 days

1 Answer

+1 vote
by (71.7k points)
selected by
 
Best answer

Correct option (a) 12 days

Explanation: 

20 → 18 days 

Work done by 20 men working together = 1 work 

Work done by them in 3 days working together = 1×3=3 work 

Remaining work =18-3=15 work 

15 work is to be done by (20+5)=25 men 

 Efficiency of 20 men= 1 

Efficiency of 1 men = 1/20

Therefore, 12 more days will be taken to finish the remaining work

Alternate:- 20 men can do 18 days 

So total work = 18×20 =360 

20 men 3 days work = 20×3 =60 

Remaining work = 360-60=300 

After joining 5 men total men = 20+5

so 300/25 = 12 days

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.