A and B working separately can do a piece of work in 9 and 12 days respectively, If they work for a day alternately, A beginning, in how many days, the work will be completed?

1 Answer

+1 vote
by (57.6k points)
selected by
 
Best answer

(A + B)'s 2 days' work =(1/9+1/12)=7/36 

Work done in 5 pairs of days =(5*7/36)=35/36  

Remaining work =(1-35/36)=1/36 

On 11th day, it is A’s turn. 1/9 work is done by him in 1 day. 

1/36 work is done by him in(9*1/36)=1/4 day

Total time taken = (10 + 1/4) days = 10 1/4days.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.