To complete a piece of work, A takes 50% more time than B. If together they take 18 days to complete the work, how much time will B take to do it? 

(a) 30 days 

(b) 35 days 

(c) 40 days 

(d) 45 days

1 Answer

+1 vote
by (71.7k points)
selected by
 
Best answer

Correct option (a) 30 days

Explanation: 

efficiency of work = 2 : 3 (Time and efficiency inversely proportion to each other)

Total work = 18days ×(2+3) unit = 90 unit

B Completes the work 

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.