P is thrice as good a workman as Q and therfore able to finish a job in 48 days less than Q. working together, they can do it in :

 (a) 18 days 

(b) 24 days 

(c) 30 days 

(d) 12 days

1 Answer

+1 vote
by (71.7k points)
selected by
 
Best answer

Correct option (a) 18 days

Explanation: 

Total work = No. of days× efficiency = 72×1 = 72 

One day work of P and Q is 3+1= 4 units. 

(P+Q) will complete the work in 

= 72/4 = 18 days

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.