A takes three times as long as B and C together to do a job. B takes four times as long as A and C together to do the work. If all the three, working together can complete the job in 24 days, then the number of days. A alone will take to finish the job is: 

(a) 100 

(b) 96 

(c) 95 

(d) 90 

1 Answer

+1 vote
by (71.7k points)
selected by
 
Best answer

Correct option (b) 96

Explanation: 

Correct option Explanation: 

Since we know, efficiency of a person’s will know, efficiency of a person’s will remain same. So we will balance it.

A’s efficiency : 5 units

B’s efficiency : 4 units

Total efficiency : 20 units

So, C’s efficiency 20 – 5 – 4 = 11 units

Total work = 24days × 20units/day

480 units.

A alone will do whole work in 480/5 = 96 days

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.