A and B can complete a piece of work in 12 and 18 days respectively. A begins to do the work and they work alternatively one at a time for one day each. The whole work will be completed in: 

(a) 43/3 days 

(b) 46/3 days 

(c) 48/3 days 

(d) 56/3 days

1 Answer

+1 vote
by (71.7k points)
selected by
 
Best answer

Correct option (a) 43/3 days

Explanation: 

A’s one day work = 3 units

B’s one day work = 2 units

A starts the work and does 3 units and B does the work 2 units/days

They both do 5 units of work in 2 days. They both do 35 units of work in 14 days

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.