40 men can complete a piece of work in 40 days. They started the work together. But at the end of each 10 thday, 5 men left the job. The work would have been completed in 

(a) 170/3 days 

(b) 160/3 days 

(c) 52 days 

(d) 50 days

1 Answer

+1 vote
by (71.7k points)
selected by
 
Best answer

Correct option (a) 170/3 days

Explanation: 

Let a man can do 1 unit/day. 

Total work = 40men×40days=1600 units 

40 men can do the work in 10 days = 400 units 

According to question, (5 men left after 10 days) 

35 men can do the work in 10 days = 350 units 

30 men can do the work in 10 days = 300 

25 men can do the work in 10 days = 250 

20 men can do the work in 10 days = 200 

Men left 20-5 = 15 and work left = 1600- 1500 = 100 units they will complete in

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.