a = 6000 hrs., 1 lot = 30 engines, x = 120 engines = 4 lots
Table method
Total time taken to produce 120 engines = 15360
Time taken to produce 30 engines = 6000
Total time taken to produce 90 engines
= 15360 – 6000 = 9360
Labour cost at Rs 20 per hour = 9360 × 20 = 1,87,200
Formula Method
a = 6000 hours, x = 4,
y = axb
log y = log a + b log x
= log 6000 – 0.3219 x log 4
= 3.7782 – 0.3219 × 0.6021 = 3.7782 – 0.1938 = 3.5844
y = A.L (3.5844) = 3841
Total number of hours required to produce 4 lots (120 engines)
= 3841 × 4 = 15364 hours.
∴ Total number of hours required to produce 90 engines
= 15364 – 6000 = 9364 hrs.
Labour cost at Rs 20 per hour = 20 × 9364 = Rs 1,87,280