A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs. 200 for the first day. Rs. 250 for the second day. Rs. 300 for the third day. etc.. the penalty for each succeeding day being Rs. 50 more than for the preceding day. How much money the contractor has to pay as penalty. If he has delayed the work by 30 days?

1 Answer

0 votes
by (65.2k points)
selected by
 
Best answer

Penalty for the 1st Day 2nd day 3rd day … 30th day 

Rs. 200 Rs. 250 Rs. 300 Rs.? 

200 + 250 + 300 + 30 days 

a = 200, d = 250 – 200 = 50, n = 20, 

S30 = ?

= 15[400 + 29 × 50] 

= 15 [400 + 1450] 

= 15 × 1850 

∴ S30 = Rs. 27750.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.

...