Explain 

1. Lead time-t 

2. Holding cost-C1 

3. Set up cost-C

4. shortage cost-C2

1 Answer

+1 vote
by (57.2k points)
selected by
 
Best answer

Lead time – t: The time gap between placing of order and arrival of goods at the inventory is the Lead time 

Holding cost – C1: It is the cost associated with carrying or holding the goods in stock until the goods are sold or used. It includes rent for space, interest on capital, maintenance of records, taxes, insurance etc. 

Setup cost – C3: It is the cost of setting up the machines for production or the cost of 4 placing the order for the goods. It includes labour cost, transportation cost etc. It is also called as Ordering cost. 

Shortage cost – C2: The cost associated with delay or inability to meet the demand, because  of shortage of Stock is called shortage cost Or penalty cost..

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.