11 men can dig 6 3/4 metre long trench in one day. How many men should be employed for digging 27 metre long trench of the same type in one day?

1 Answer

+1 vote
by (30.5k points)
selected by
 
Best answer

Let’s consider number of men required be ‘x’ men

Length of trench (m) 27/4 27
Number of men 11 x

(27/4)/11 = 27/x

By cross-multiplying

x27/4 = 27(11)

x27/4 = 297

x = (297 × 4)/27

= 44

∴ To dig 27 m long trench of same type in one day requires 44 men.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.