If 36 men can do a piece of work in 25 days, in how many days will 15 men do it?

1 Answer

+1 vote
by (30.5k points)
selected by
 
Best answer

Let the number of days required by men to do piece of work be ‘x’ days

Men 36 15
Time (days) 25 x

We know k = xy

36 × 25 = 15 × x

x = (36×25)/15

= 60

∴ 15 men require 60days to do a piece of work.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.