A work force of 50 men with a contractor can finish a piece of work in 5 months. In how many months the same work can be completed by 125 men?

1 Answer

+1 vote
by (30.5k points)
selected by
 
Best answer

Let the number of months required by men to finish a piece of work be ‘x’ months

Men 50 125
Time (months) 5 x

We know k = xy

50 × 5 = 125 × x

x = (50×5)/125

= 2

∴ 125 men require 2 months to do a piece of work.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.