A work-force of 420 men with a contractor can finish a certain piece of work in 9 months. How many extra men must he employ to complete the job in 7 months?

1 Answer

+1 vote
by (30.5k points)
selected by
 
Best answer

Let the number of men required be ‘x’ men

Total men = 420

Men 420 x
Time (months) 8 7

We know k = xy

420 × 9 = x × 7

x = (420×9)/7

= 540

So, 540 – 420 = 120 Men

∴ 120 extra men are required to finish the job in 7 months.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.