A person has undertaken a construction job. The probabilities are 0.65 that there will be strike, 0.80 that the construction job will be completed on time if there is no strike and 0.32 that the construction job will be completed on time if there is a strike. Determine the probability that the construction job will be completed on time.

1 Answer

+1 vote
by (46.3k points)
selected by
 
Best answer

Probability that there will be strike 

P(A) = 0.65 

Probability that there will not be strike 

P(\(\bar{A}\)) = 1 – 0.65 = 0.35 

Let E the event that work finished in time. 

Then probability of completion of work in strike. 

P (E/A) = 0.32 

and probability of completion of work when there is no strike 

P (E/A) = 0.80 

∴ Probability that the construction job will be completed on time

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.

...