A firm's SMC schedule is shown in the following table. The total fixed cost of the firm is Rs. 100.00. Find the TVC, TC, AVC and SAC schedules of the firm.

Output 1 2 3 4 5 6
TC 50 65 75 95 130 185

1 Answer

0 votes
by (150k points)
selected by
 
Best answer
Output(units)  SMC(Rs.) TFC(Rs.) TVC(Rs.) TC(Rs.) AVC(Rs.) SAC(Rs.)
0 - 100 0 100 - -
1 500 100 500 600 500 600
2 300 100 800 900 400 450
3 200 100 1000 1100 333.33 366.67
4 300 100 1300 1400 325 350
5 500 100 1800 1900 360 380
6 800 100 2600 2700 433.33 450

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.