Five workers take 12 days to weed a field. How many days would 6 workers take? How many would 15 take?

1 Answer

+1 vote
by (47.6k points)
selected by
 
Best answer

Let 6 workers take x days and 15 workers take y days to weed the field. 

The number of workers and the time required to weed the field are in inverse proportion. 

∴ 6 × x = 5 × 12 

∴ x = (5 x 12)/6

∴ x = 10 days

Also, 

15 × y = 5 × 12 

∴ y = (5 x 12)/15 

= 4 days 

∴ 6 workers will take 10 days and 15 workers will take 4 days to weed the field.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.

...