Forward pass:
E1 = 0
E2 = 0 + 6 = 6
E3 = 0 + 5 = 5
E4 = 6 + 10 = 16
E5 = (E4 + 6) (or) (E3 + 4)
E5 = (16 + 6) (or) (5 + 4) [whichever is maximum]
E5 = 22
E6 = (E5 + 9) (or) (E4 + 2)
E6 = (22 + 9) (or) (4 + 2) [whichever is maximum]
E6 = 31
Backward pass:
L6 = 31
L5 = 31 – 9 = 22
L4 = 22 – 6 (or) 31 – 2 [whichever is minimum]
L4 = 16
L3 = 22 – 4 = 18
L2 = 16 – 10 = 6
L1 = 6 – 6 = 0
EFT and LFT are the same on 1-2, 2-3, 3-4, and 4-5
So critical path is 1-2-3-4-5 and the time taken is 24 days.