The following table gives the activities of a project and their duration in days.

Activity 1-2 1-3 2-3 2-4 3-4 3-5 4-5
Duration 5 8 6 7 5 4 8

Construct the network and calculate the earliest start time, earliest finish time, latest start time, and latest finish time of each activity and determine the critical path of the project and duration to complete the project.

1 Answer

+1 vote
by (26.4k points)
selected by
 
Best answer

Forward pass:

E1 = 0

E2 = 0 + 6 = 6

E3 = 0 + 5 = 5

E4 = 6 + 10 = 16

E5 = (E4 + 6) (or) (E3 + 4)

E5 = (16 + 6) (or) (5 + 4) [whichever is maximum]

E5 = 22

E6 = (E5 + 9) (or) (E4 + 2)

E6 = (22 + 9) (or) (4 + 2) [whichever is maximum]

E6 = 31

Backward pass:

L6 = 31

L5 = 31 – 9 = 22

L4 = 22 – 6 (or) 31 – 2 [whichever is minimum]

L4 = 16

L3 = 22 – 4 = 18

L2 = 16 – 10 = 6

L1 = 6 – 6 = 0

EFT and LFT are the same on 1-2, 2-3, 3-4, and 4-5 

So critical path is 1-2-3-4-5 and the time taken is 24 days.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.

...