The following table uses the activities in construction projects and relevant information.

Activity 1-2 1-3 2-3 2-4 3-4 4-5
Duration (in days) 22 27 12 14 6 12

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time, and latest finish time of each activity, and find the critical path. Compute the project duration.

1 Answer

+1 vote
by (26.4k points)
selected by
 
Best answer

Forward pass:

E1 = 0

E2 = 0 + 22 = 22

E3 = (0 + 27) (or) (22 + 12) = 34 [Maximum of both]

E4 = (22 + 14) (or) (34 + 16) = 40

E5 = 40 + 12 = 52

Backward pass:

L5 = 32

L4 = 52 – 12 = 40

L3 = 40 – 6 = 34

L2 = (40 – 14) (or) (34 – 12) = 22 [Minimum of both]

L1 = 22 – 22 = 0

EFT and LFT are the same for 1-2, 2-3, 3-4, and 4-5. 

So critical path is 1-2-3-4-5 time to complete is 52 days.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.

...