Use app×
Join Bloom Tuition
One on One Online Tuition
JEE MAIN 2025 Foundation Course
NEET 2025 Foundation Course
CLASS 12 FOUNDATION COURSE
CLASS 10 FOUNDATION COURSE
CLASS 9 FOUNDATION COURSE
CLASS 8 FOUNDATION COURSE
0 votes
3.4k views
in Operations Research by (26.1k points)
closed by

The critical path of the following network is:

(a) 1-2-4-5 

(b) 1-3-5 

(c) 1-2-3-5 

(d) 1-2-3-4-5

1 Answer

0 votes
by (26.4k points)
selected by
 
Best answer

(d) 1-2-3-4-5

1-2-4-5 ⇒ EFT = 20 + 12 + 10 = 42 

1-3-5 ⇒ EFT = 25 + 8 = 33 

1-2-3-5 ⇒ EFT = 20 + 10 + 8 = 38 

1-2-3-4-5 ⇒ EFT = 20 + 10 + 5 + 10 = 45

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.

...