One of the conditions for the activity (i, j) to lie on the critical path is:

(a) Ej – Ei = Lj – Li = tij

(b) Ei – Ej = Lj – Li = tij

(c) Ej – Ei = Li – Lj = tij

(d) Ej – Ei = Lj – Li ≠ tij

Please log in or register to answer this question.

1 Answer

+1 vote
by (26.4k points)

(a) Ej – Ei = Lj – Li = tij

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.

...