Working individually, A and B can complete a piece of work in 30 days and 45 days respectively. If B joins A after some days and the whole work is completed in 20 days from the beginning, after how many days does B join A ?
A. 15
B. 10
C. 5
D. 12

1 Answer

0 votes
by (106k points)
selected by
 
Best answer
Correct Answer - C
A, on the whole workes for 20 days. Let B work for (20-x) days.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.