The ‘centre line method’ is specially adopted for estimating?

(a) Circular buildings

(b) Hexagonal buildings

(c) Other geometrical shaped buildings

(d) Circular, hexagonal and other geometric shapes

1 Answer

0 votes
by (120k points)
selected by
 
Best answer
Correct choice is (d) Circular, hexagonal and other geometric shapes

Explanation: By center-line method, estimate for earthwork, concrete work or brick work for all walls of the building can be done at a time. If there are junctions, it needs to be carefully calculated deducting the widths. By long wall and short wall method, each wall is estimated separately. In centerline method, it can be prepared quickly eliminating lengthy mathematical calculations.  In Center-line method, estimate can’t be physically measured at site where as it can be done for Long wall short wall method. Center-line method is preferred for preparing estimates and long wall short wall method is preferred for entering measurements in measurement book.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.