Requirements Management has a high initial start-up cost but does not need ongoing funding throughout a project.

(a) True

(b) False

This question was posed to me in semester exam.

This interesting question is from Requirement Management topic in division Requirement Engineering of Software Engineering

1 Answer

0 votes
by (120k points)
selected by
 
Best answer
Correct answer is (b) False

The best explanation: Requirements Management needs continued funding throughout a project.Project funding is often limited at the onset of a project, restricted to those aspects of the project which are tangible and visible, and subsequently allocated in a phase-by-phase manner.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.