Correct Answer - Option 3 : 80 – 150 mm
Explanation
Workability of Concrete:
The concrete mix proportions chosen should be such that the concrete is of adequate workability for the placing conditions of the concrete and can properly be compacted with the means available.
For concrete work, low workable concrete is preferred.
Normal RCC work = (80 – 150) mm
Mass concrete = (20 – 50) mm
Columns and slabs = (40 – 50) mm