The minimum period before stripping the formwork for props to slabs spanning 6 m is
1. 16 - 24 h
2. 3 days
3. 7 days
4. 21 days
5. 14 days

1 Answer

0 votes
by (101k points)
selected by
 
Best answer
Correct Answer - Option 5 : 14 days

As per IS 456: 2000 clause 11.3,

Type of Formwork Minimum period before
Vertical formworks to columns, walls, and beams 16-24 hrs
Soffit formworks to slabs 3 days
Soffit formworks to beams 7 days
Props to the slab for spanning up to 4.5 m 7 days
Props to the slab for spanning over 4.5 m 14 days
Props to beams and arches spanning up to 6 m 14 days
Props to beams and arches spanning over 6 m 21 days

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.