40 men are hired to make 1000 PPE kits in 30 days, but after 20 days they found out that they could only complete 400 clothes. How many more men are needed so that they can complete their work on time?


1. 60 men
2. 70 men
3. 100 men
4. 80 men

1 Answer

0 votes
by (98.6k points)
selected by
 
Best answer
Correct Answer - Option 4 : 80 men

Given:

M1 = 40

W1 = 400

D1 = 20 days

Formula used:

(M1 × D1)/W1 = (M2 × D2)/W2

Where, M represents number of men, D represents number of days, and W represents the work (Number of PPE kits made)

Calculation:

Let number of extra men needed be x

M2 = 40 + x

W2 = 1000 – 400 = 600

(M1 × D1)/W1 = (M2 × D2)/W2

⇒ (40 × 20)/400 = (M2 × 10)/600

⇒ 800/400 = (40 + x)/60

⇒ 40 + x = 120

⇒ x = 12 – 40 = 80

80 extra men are needed to complete the work on time.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.