Correct Answer - Option 4 : 80 men
Given:
M1 = 40
W1 = 400
D1 = 20 days
Formula used:
(M1 × D1)/W1 = (M2 × D2)/W2
Where, M represents number of men, D represents number of days, and W represents the work (Number of PPE kits made)
Calculation:
Let number of extra men needed be x
M2 = 40 + x
W2 = 1000 – 400 = 600
(M1 × D1)/W1 = (M2 × D2)/W2
⇒ (40 × 20)/400 = (M2 × 10)/600
⇒ 800/400 = (40 + x)/60
⇒ 40 + x = 120
⇒ x = 12 – 40 = 80
∴ 80 extra men are needed to complete the work on time.