Statement (I): Bar chart plots in the time dimension the planned performance of various activities of a project.
Statement (II): One advantage of a bar chart is that the inter se sequence and linkage of all activities is indicated therein.
1. Both Statement (I) and Statement (II) are individually true and Statement (II) is the correct explanation of Statement (I)
2. Both Statement (I) and Statement (II) are individually true but Statement (II) is not the correct explanation of Statement (I)
3. Statement (I) is true but Statement (II) is false
4. Statement (I) is false but Statement (II) is true