Correct Answer - Option 3 : 0.73
As 5.5 bags of cement can produce 1 m3 of concrete.
For 0.8 m3 of concrete, bags required are 5.5 x 0.8 =4.4 bags
Hence 4 bags are required.
The maximum number of full bags will be 4. So 4 bags can produce \(\frac{4}{{4.4}}*0.8 = 0.73\) m3 of concrete.