Correct Answer - Option 1 : 75
Given:
A certain number of persons can do a piece of work in 40 days
Formula used:
M1D1 = M2D2
Where,
M1 = Men1 , D1 = Days1
M2 = Men2 , D2 = Days2
Calculation:
Let be the x persons were employed to do the work initially,
If 45 persons more = (x + 45)
According to the question,
M1D1 = M2D2
⇒ x × 40 = (x + 45) × 25
⇒ x × 40 = 25x + 1125
⇒ 15x = 1125
⇒ x = 75
∴ 75 persons were employed to do the work initially.