A alone can complete the work in 12 days and B alone can complete the work in 24 days. When A, B and C worked together then work will be completed in 72/11 days. In how many days C alone can complete the half of the work?
1. 18 days
2. 72 days
3. 36 days
4. 40 days

1 Answer

0 votes
by (114k points)
selected by
 
Best answer
Correct Answer - Option 1 : 18 days

Given:

A can do the work in 12 days

B can do the work in 24 days

A, B, C can do the work in 72/11 days

Calculation:

A's 1 days work = 1/12

B's 1 days work = 1/24

⇒ (A + B + C)'s 1 days work = 1/12 + 1/24 + 1/C

⇒ 1/12 + 1/24 + 1/C = 11/72

⇒ 1/C = 1/36

C alone can complete the work in 36 days.

∴ Time taken by C to complete half of work = 36 × 1/2 = 18 days

Time taken by a person to complete a/b fraction of work = a/b × (Number of days in which person alone can complete work)

 

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.