Rohan can do a piece of work in 16 days. Rohit is twice as efficient as Rohan. In how many days will Rohit complete the work?
1. 6 days
2. 4 days
3. 8 days
4. 2 days

1 Answer

0 votes
by (114k points)
selected by
 
Best answer
Correct Answer - Option 3 : 8 days

Given:

Rohan can do a piece of work = 16 days

The efficiency of Rohit = twice as Rohan

Calculation:

Let, efficiency of Rohan = x/day

∴ Efficiency of Rohit = 2x/day

Let, Rohit can complete the work in = y days

According to the question,

⇒ 16x = 2xy

⇒ 2y = 16

⇒ y = 8

∴Rohit will complete the work in = 8 days

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.