Ram is twice as good a workman as Sham and is therefore able to finish a piece of work in 16 days less than Sham. In how many days they can complete the whole work by working together?
1. 12 days 
2. 13 days 
3. 10(2/3) days
4. 11 days 
5. None of these 

1 Answer

0 votes
by (114k points)
selected by
 
Best answer
Correct Answer - Option 3 : 10(2/3) days

Given:

Ram is twice as good a workman as Sham

Ram can finish a piece of work in 16 days less than Sham

Formula:

(A + B)’s 1 day work = 1/A + 1/B

Calculation:

Ratio of times taken by Ram and Sham = 1 : 2.

The time difference is (2 - 1) = 1 days

Sham take 2 days and Ram takes 1 day.

If difference of time is 1 day, B takes 2 days.

If difference of time is 16 days,

Sham takes 2 x 16 = 32 days.

So, Ram takes 16 days to do the work.

Ram's 1 day's work = 1/32

Sham's 1 day's work = 1/16

(Ram + Sham)'s 1 day's work = 1/32 + 1/16 = 3/32 work

⇒ 32/3 days = 10(2/3)

∴ Ram and Sham together can do the work in 10(2/3) days.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.