39 persons can repair a road in 12 days, working 5 hours a day. In how many days will 30 persons, of same efficiency working 6 hours a day, complete the work ?
1. 10
2. 13
3. 14
4. 15

1 Answer

0 votes
by (115k points)
selected by
 
Best answer
Correct Answer - Option 2 : 13

Given :

M1 = 39 person , M2 = 30 persons

D= 12 days , D2 = ?

H1 = 5 hours , H 2 = 6 hours 

Formula used :

M× D1 × H/ work1   = M2 × D2 × H 2 / work2

Calculation : 

Substituting the values in the formula

39 x 5 x 12  = 30 ×  6 ×  days

⇒ 2340 = 180 × days 

⇒ days = 2340 / 180 = 13 

 ∴ 30 persons will complete the work in 13 days. 

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.