Correct Answer - Option 2 : Rs. 43,20,000
The correct answer is option 2.
Given data, Functional Point=864
team=6 persons
average each peson(FP) productivity=12
designer month salary=70000
programmers month salary=2x60000
tester month salary=2x60000
Requirement gatherer=50000
Projected cost of project=?
Total number of months=\(\frac{Functional Point(FP)}{(Team \times Average each person (FP) productivity)}\)= \(\frac{864}{6\times12}\)
=12 months
Total cost of the project=(one designer salary+2 x Programmer month salary+2 x tester month salary+one requirement gatherer) x total number of months
=(70000+2x60000+2x60000+50000)x12
=43,20,000
∴ Hence the correct answer is Rs. 43,20,000.