Correct Answer - Option 4 : 80 m
Concept:
Total Grade = Grade 1 – Grade 2
Length of curve = (Total grade/Rate of change of grade per chain length) × Length of chain
Calculation:
An upgrade of + 1.2% joins another upgrade of + 0.8%.
Grade = + 1.2 – (+ 0.8) = 0.4 % (Upward)
Change of grade is 0.1% per 20 m chain.
L = (0.4/0.1) × 20 =
80 m