0 votes
80 views
in Mathematics by (237k points)
closed by
If A, B and C alone can complete a work in x, y and z days respectively, then in how many days will they complete the same work, working together?
1. \(\frac{{x + y + z}}{{xyz}}\) days
2. \(\frac{{xy + yz + zx}}{{xyz}}\) days
3. \(\frac{{xyz}}{{xy + yz + zx}}\) days
4. None of the above

1 Answer

0 votes
by (239k points)
selected by
 
Best answer
Correct Answer - Option 3 : \(\frac{{xyz}}{{xy + yz + zx}}\) days

Calculation

A can complete work in 'x' days

B can complete work in 'y' days

C can complete work in 'z' days

A's one-day work = 1/x

B's one-day work = 1/y

C's one-day work = 1/z

A, B and C's one-day work = 1/x + 1/y + 1/z

\(\Rightarrow {xy + yz + zx \over xyz}\)

Time taken by A, B and C together to complete the work = 1/A, B and C's one-day work

\(\Rightarrow \frac{{xyz}}{{xy + yz + zx}} days\)

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.