Correct Answer - Option 2 : Task
Concept:
Work Breakdown Structure (WBS):
- The Project Work Breakdown Structure is an outcome-oriented analysis of the work involved in the project and defines the total scope of the project.
- It is a foundation document in project management because it provides the basis for planning and managing the project schedule, budget, and requests for changes.
- A WBS also provides the necessary framework for detailed cost estimating.
- Task or activities is the smallest level of the Work Breakdown Structure.
Different levels of WBS:
- Project titles
- Control accounts
- Work packages
- Task or activities
How to Make a Work Breakdown Structure:
- Gather critical Documents
- Identify key team members
- Define the elements
- breakdown of elements
- Create WBS dictionary
- Create chart schedule