Which of the following is at the lowest level as per WBS?
1. Project
2. Task
3. Work package
4. Sub project

1 Answer

0 votes
by (121k points)
selected by
 
Best answer
Correct Answer - Option 2 : Task

Concept:

Work Breakdown Structure (WBS):

  • The Project Work Breakdown Structure is an outcome-oriented analysis of the work involved in the project and defines the total scope of the project.
  •  It is a foundation document in project management because it provides the basis for planning and managing the project schedule, budget, and requests for changes.
  • A WBS also provides the necessary framework for detailed cost estimating.
  • Task or activities is the smallest level of the Work Breakdown Structure.

Different levels of WBS:

  • Project titles 
  • Control accounts
  • Work packages
  • Task or activities

How to Make a Work Breakdown Structure:

  • Gather critical Documents
  • Identify key team members
  • Define the elements
  • breakdown of elements
  • Create WBS dictionary 
  • Create chart schedule

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.