Three persons undertake to complete a piece of work for 1200. The first person can complete the work in 8 days, second person in 12 days and third person in 16 days, They complete the work with the help of a fourth person in 3 days, What does the fourth person get?
(a) Rs. 180
(b) Rs. 200
(c) Rs. 225
(d) Rs. 250