210 men working 12 hours a day can finish a job in 18 days. How many men are required to finish the job in 20 days working 14 hours a day?

1 Answer

+1 vote
by (44.5k points)
selected by
 
Best answer

Let the required number of men be x.

More working hours ⇒ less men required.

∴ It is inverse proportion.

∴ Multiplying factor is 12/14

Also more number of days ⇒ less men

∴ It is an inverse proportion.

∴ Multiplying factor is 18/20

∴ x = 210 × 12/14 × 18/20 = 162 men

162 men are required.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.