A soap factory produces 9600 soaps in 6 days working 15 hours a day. In how many days will it produce 14400 soaps working 3 hours more a day?

1 Answer

+1 vote
by (44.5k points)
selected by
 
Best answer

Let the required number of days be x.

To produce more soaps more days required.

∴ It is direct proportion.

∴ Multiplying factor = 14400/9600

If more hours spend, less days required.

∴ It is indirect proportion.

∴ Multiplying factor = 15/18

∴ x = 6 × 14400/9600 × 15/18

x = 15/2

15/2 days will be needed.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.