Correct Answer - Option 1 : 24
Given:
A certain number of men complete the work in 60 days.
When 8 men join, work completed 15 days earlier,
Means (60 - 15) = 45days
Concept used:
Total work = Total Manpower × Days
M1 × D 1 = M2 × D2
Calculation:
Let the number of men originally be N
According to the question,
⇒ N × 60 = (N + 8) × 45
⇒ N × 60 = N × 45 + 360
⇒ N × 15 = 360
⇒ N = 24
∴ The number of men originally is '24'.