Which one of the following does have some limitations when applied to detailed engineering design work during early stages of a project?


1. CPM
2. PERT
3. Dummy activity
4. Estimate

1 Answer

0 votes
by (108k points)
selected by
 
Best answer
Correct Answer - Option 1 : CPM

Concept

Dummy Activity: An activity which is used to maintain the predefined precedence relationship only during the construction of the project network is called a dummy activity.

Estimate: An approximate calculation or judgement of value

PERT is preferred when there is some uncertainties in the methodology, availability of materials, and the final answer is not clearly known.

Whereas CPM is applied when things are almost certain

Example in case of a construction project, once the project has been finalized there is little doubt of men, material and equipment required, time etc. then PERT is used

∴ CPM has limitations in the early stage of project.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.