Use app×
Join Bloom Tuition
One on One Online Tuition
JEE MAIN 2025 Foundation Course
NEET 2025 Foundation Course
CLASS 12 FOUNDATION COURSE
CLASS 10 FOUNDATION COURSE
CLASS 9 FOUNDATION COURSE
CLASS 8 FOUNDATION COURSE
0 votes
206 views
in General by (108k points)
closed by

Statement (I): In a multipath PERT network, the project duration resulting from the critical path always has a 50% probability of completion by that duration.

Statement (II): The expected - path duration together with 3-times the standard deviation of that expected duration must be considered for all the paths in the network. 


1. Both Statement (I) and Statement (II) are individually true and Statement (II) is the correct explanation of Statement (I)
2. Both Statement (I) and Statement (II) are individually true but Statement (II) is not the correct explanation of Statement (I)
3. Statement (I) is true but Statement (II) is false
4. Statement (I) is false but Statement (II) is true

1 Answer

0 votes
by (101k points)
selected by
 
Best answer
Correct Answer - Option 3 : Statement (I) is true but Statement (II) is false

Statement I: True

The probability of completion of project for any time say Ts is decided by a factor called probability density function and it is given as:

\(Z = \frac{{{T_S} - {T_E}}}{\sigma }\)

Where,

σ is the standard deviation

Ts is the scheduled completion of project

TE is the expected completion time

The relation between Z and probability of completion of work is given as:

Z values

-3

-2

-1

0

1

2

3

P Values (%)

0.13

2.28

15.67

50

84.13

97.72

99.87


It is clear from the above table that If Ts = TE i.e. the project duration resulting from the critical path always has a 50% probability of completion by that duration.

Statement II: False

PERT is based on the probabilistic approach and in this three-time estimates namely – Optimistic time (To), Pessimistic time (Tp), and most likely time (TL) is considered for each activity in the path.

The expected or average duration (TE) of each activity is the weighted average of these three-time durations.  This  TE and standard deviation σ are considered together for each activity in the path network. 

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.

Categories

...