Correct Answer - Option 3 : Statement (I) is true but Statement (II) is false
Statement I: True
The probability of completion of project for any time say Ts is decided by a factor called probability density function and it is given as:
\(Z = \frac{{{T_S} - {T_E}}}{\sigma }\)
Where,
σ is the standard deviation
Ts is the scheduled completion of project
TE is the expected completion time
The relation between Z and probability of completion of work is given as:
Z values
|
-3
|
-2
|
-1
|
0
|
1
|
2
|
3
|
P Values (%)
|
0.13
|
2.28
|
15.67
|
50
|
84.13
|
97.72
|
99.87
|
It is clear from the above table that If Ts = TE i.e. the project duration resulting from the critical path always has a 50% probability of completion by that duration.
Statement II: False
PERT is based on the probabilistic approach and in this three-time estimates namely – Optimistic time (To), Pessimistic time (Tp), and most likely time (TL) is considered for each activity in the path.
The expected or average duration (TE) of each activity is the weighted average of these three-time durations. This TE and standard deviation σ are considered together for each activity in the path network.