Correct Answer - Option 2 : 30 days
Given
Karan and Arjun completes a work in 24 days
Karan completes a work in 120 days
Calculation
Let the work done by Arjun is x days
Work done by Karan and Arjun in 1 day = 1/24
Work done by Karan in 1 day = 1/120
Work done by Arjun in 1 day = 1/x
(1/120) + (1/x) = (1/24)
⇒ (1/x) = (1/24) - (120)
⇒ (1/x) = (5 - 1)/120
⇒ (1/x) = 4/120
⇒ x = 30 days
∴ Arjun completes a work in 30 days