Correct Answer - Option 2 : 4
Calculation:
A + B can complete the work in x days,
A alone can complete in x + 2 days
B alone can complete in x + 8 days
Work done by A in 1 day = 1/(x + 8)
Work done by B in 1 day = 1/(x + 2)
Work done by A + B in 1 days = 1/x
⇒ 1/x = 1/(x + 8) + 1/(x + 2)
⇒ 1/x = (2x + 10)/(x2 + 10x + 16)
⇒ x = (x2 + 10x + 16)/(2x + 10)
⇒ 2x2 + 10x = x2 + 10x + 16
⇒ x2 = 16
∴ x = + 4 or - 4
But days can not be negative, hence x = 4 days