Correct Answer - Option 2 : 1 : 3
Given:
By four more men work will complete in 8 days before.
Calculation:
Let the number of men be x and the number of days they take to complete the job be y.
⇒ (x + 4) × (y - 8) = xy
⇒ 4y - 8x = 32 .... (1)
⇒ (x + 8) × (y - 12) = xy
⇒ 8y - 12x = 96 .... (2)
Solving the equation (1) and (2)
⇒ x = 8, y = 24, now ratio become = 8 : 24 = 1 : 3