If Anand can do ¼th work in 3 days and Badal can do 1/6th work in 4 days, how much will Anand get if both work together and are paid Rs. 3600 in all?


1. Rs 2500
2. Rs 2400
3. Rs 2000
4. Rs 1600
5. Rs 1200

1 Answer

0 votes
by (114k points)
selected by
 
Best answer
Correct Answer - Option 2 : Rs 2400

Solution:

Calculations:

Anand does 1/4th work = 3 days

∴The whole work is done by Anand in = 3 × 4

⇒ 12 days

Badal does 1/6th work = 4 days

∴The whole work is done by Badal in = 4 × 6

⇒ 24 days

∴Anand’s wages : Badal’s wages = Anand’s 1 day’s work : Badal’s 1 day’s work

⇒ 1/12 : 1/24

⇒ 24 : 12

⇒ 2 : 1

∴Anand’s share = 2/3 × 3600

⇒ 2 × 1200

⇒Rs. 2400

Anand will get Rs. 2400.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.