Correct Answer - Option 4 : 90 minutes
Given:
Time taken by pipe X to fill the tank = 30 minutes
Time taken by pipe Y to fill the tank = 45 minutes
Time taken by pipe Z to empty the tank = 60 minutes
Working time of (X + Y) = 10 minutes
Concept:
Consider the total work to be 1 unit. Take the sign of Z as negative because it empties the tank.
Formula used:
1 unit work = 1/(Total time taken to complete the work)
Calculation:
(X + Y)'s 1 min work = (1/30) + (1/45)
= (3 + 2)/90
= 5/90
∴ Unit of work done by (X + Y) in 10 min = (10 × 5)/90
= 50/90
Unit of work left = 1 - (50/90)
= (90 - 50)/90
= 40/90
This work will be done by Y and Z together.
(Y - Z)'s 1 min work = (1/45) - (1/60)
= (4 - 3)/180
= 1/180
∴ Time taken by (Y and Z) to complete the whole work = 180 min
∴ Time taken by (Y and Z) to complete 40/90 unit of work = 180 × (40/90)
= 80 minutes.
∴ Total time taken to finish the whole work = (Time taken by X + Y) + (Time taken by Y and Z)
= 10 min + 80 min
= 90 min